Merge pull request #10471 from ton31337/fix/release_candidate_procedure
doc: Add a commands snippet to workflow about what to do in RC1 phase
This commit is contained in:
commit
89569a7684
@ -95,8 +95,8 @@ March/July/November. Walking backwards from this date:
|
||||
are considered lowest priority (regardless of when they were opened.)
|
||||
|
||||
- 4 weeks earlier, the stable branch separates from master (named
|
||||
``dev/MAJOR.MINOR`` at this point) and a ``rc1`` release candidate is
|
||||
tagged. Master is unfrozen and new features may again proceed.
|
||||
``dev/MAJOR.MINOR`` at this point) and tagged as ```base_X.Y``.
|
||||
Master is unfrozen and new features may again proceed.
|
||||
|
||||
Part of unfreezing master is editing the ``AC_INIT`` statement in
|
||||
:file:`configure.ac` to reflect the new development version that master
|
||||
@ -108,7 +108,38 @@ March/July/November. Walking backwards from this date:
|
||||
(The :file:`configure.ac` edit and tag push are considered git housekeeping
|
||||
and are pushed directly to ``master``, not through a PR.)
|
||||
|
||||
- 2 weeks earlier, a ``rc2`` release candidate is tagged.
|
||||
Below is the snippet of the commands to use in this step.
|
||||
|
||||
.. code-block:: console
|
||||
|
||||
% git remote --verbose
|
||||
upstream git@github.com:frrouting/frr (fetch)
|
||||
upstream git@github.com:frrouting/frr (push)
|
||||
|
||||
% git checkout master
|
||||
% git pull upstream master
|
||||
% git checkout -b dev/8.2
|
||||
% git tag base_8.2
|
||||
% git push upstream base_8.2
|
||||
% git push upstream dev/8.2
|
||||
% git checkout master
|
||||
% sed -i 's/8.2-dev/8.3-dev/' configure.ac
|
||||
% git tag -a frr-8.3-dev -m "frr-8.3-dev"
|
||||
% git push upstream frr-8.3-dev
|
||||
% git add configure.ac
|
||||
% git commit -s -m "build: FRR 8.3 development version"
|
||||
% git push upstream master
|
||||
|
||||
In this step, we also have to update package versions to reflect
|
||||
the development version. Versions need to be updated using
|
||||
a standard way of development (Pull Requests) based on master branch.
|
||||
|
||||
Only change the version number with no other changes. This will produce
|
||||
packages with the a version number that is higher than any previous
|
||||
version. Once the release is done, whatever updates we make to changelog
|
||||
files on the release branch need to be cherry-picked to the master branch.
|
||||
|
||||
- 2 weeks earlier, a ``frr-X.Y-rc`` release candidate is tagged.
|
||||
|
||||
- on release date, the branch is renamed to ``stable/MAJOR.MINOR``.
|
||||
|
||||
@ -121,15 +152,15 @@ as early as possible, i.e. the first 2-week window.
|
||||
|
||||
For reference, the expected release schedule according to the above is:
|
||||
|
||||
+------------+------------+------------+------------+------------+------------+
|
||||
| Release | 2021-11-02 | 2022-03-01 | 2022-07-05 | 2022-11-01 | 2023-03-07 |
|
||||
+------------+------------+------------+------------+------------+------------+
|
||||
| rc2 | 2021-10-19 | 2022-02-15 | 2022-06-21 | 2022-10-18 | 2023-02-21 |
|
||||
+------------+------------+------------+------------+------------+------------+
|
||||
| rc1/branch | 2021-10-05 | 2022-02-01 | 2022-06-07 | 2022-10-04 | 2023-02-07 |
|
||||
+------------+------------+------------+------------+------------+------------+
|
||||
| freeze | 2021-09-21 | 2022-01-18 | 2022-05-24 | 2022-09-20 | 2023-01-24 |
|
||||
+------------+------------+------------+------------+------------+------------+
|
||||
+---------+------------+------------+------------+------------+------------+
|
||||
| Release | 2021-11-02 | 2022-03-01 | 2022-07-05 | 2022-11-01 | 2023-03-07 |
|
||||
+---------+------------+------------+------------+------------+------------+
|
||||
| RC | 2021-10-19 | 2022-02-15 | 2022-06-21 | 2022-10-18 | 2023-02-21 |
|
||||
+---------+------------+------------+------------+------------+------------+
|
||||
| dev/X.Y | 2021-10-05 | 2022-02-01 | 2022-06-07 | 2022-10-04 | 2023-02-07 |
|
||||
+---------+------------+------------+------------+------------+------------+
|
||||
| freeze | 2021-09-21 | 2022-01-18 | 2022-05-24 | 2022-09-20 | 2023-01-24 |
|
||||
+---------+------------+------------+------------+------------+------------+
|
||||
|
||||
Each release is managed by one or more volunteer release managers from the FRR
|
||||
community. To spread and distribute this workload, this should be rotated for
|
||||
|
@ -36,21 +36,23 @@ if __name__ == "__main__":
|
||||
print("Last release was (scheduled) on %s" % last.isoformat())
|
||||
|
||||
rel = upcoming.pop(0)
|
||||
freeze, rc1, rc2 = rel - w2 * 3, rel - w2 * 2, rel - w2
|
||||
freeze, stabilization, rc = rel - w2 * 3, rel - w2 * 2, rel - w2
|
||||
|
||||
if now == rel:
|
||||
print("It's release day! 🎉")
|
||||
elif now >= rc2:
|
||||
elif now >= rc:
|
||||
print(
|
||||
"%d days until release! (rc2 since %s)"
|
||||
% ((rel - now).days, rc2.isoformat())
|
||||
"%d days until release! (RC since %s)" % ((rel - now).days, rc.isoformat())
|
||||
)
|
||||
elif now >= stabilization:
|
||||
print(
|
||||
"%d days until RC. (stabilization branch created since %s)"
|
||||
% ((rc - now).days, stabilization.isoformat())
|
||||
)
|
||||
elif now >= rc1:
|
||||
print("%d days until rc2. (rc1 since %s)" % ((rc2 - now).days, rc1.isoformat()))
|
||||
elif now >= freeze:
|
||||
print(
|
||||
"%d days until rc1, master is frozen since %s"
|
||||
% ((rc1 - now).days, freeze.isoformat())
|
||||
"%d days until stabilization branch, master is frozen since %s"
|
||||
% ((stabilization - now).days, freeze.isoformat())
|
||||
)
|
||||